Friday, May 27, 2011

When is a liquidated damages clause valid and enforceable?

  
WHAT IS A LIQUIDATED DAMAGES PROVISION IN A CONTRACT?
 
A valid liquidated damages clause estimates in advance the just compensation a party will accrue if the other party to the contract fails to perform. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 664 (Tex. 2005). “Whether a contractual provision is an enforceable liquidated damages provision or an unenforceable penalty is a question of law[.]” Phillips v. Phillips, 820 S.W.2d 785, 788 (Tex. 1991).
 
ENFORCEABILITY OF CONTRACTUAL LIQUIDATED DAMAGES PROVISION
 
In determining whether a liquidated damages clause is enforceable, courts examine (1) whether the harm caused by the prospective breach of the contract is incapable or difficult of estimation and (2) whether the amount of liquidated damages called for is a reasonable forecast of just compensation. Id. If either element is lacking, the liquidated damages clause is unenforceable. Arthur’s Garage, Inc. v. Racal-Chubb Sec. Sys., Inc., 997 S.W.2d 803, 810 (Tex. App.—Dallas 1999, no pet.).
  
Evidence regarding the difficulty of estimating damages and whether the amount of liquidated damages is a reasonable forecast of just compensation, must be viewed as of the time the contract was executed. Baker v. Int’l Record Syndicate, Inc., 812 S.W.2d 53, 55 (Tex. App.—Dallas 1991, no writ) (op. on reh’g); see also Oetting v. Flake Unif. & Linen Serv., Inc., 553 S.W.2d 793, 796 (Tex. App.—Fort Worth 1977, no writ). “If the liquidated damages are proven to be disproportionate to the actual damages, the liquidated damages can be declared a penalty and recovery limited to actual damages.” TXU Portfolio Mgmt. Co., L.P. v. FPL Energy, LLC, 328 S.W.3d 580, 589 (Tex. App.—Dallas 2010, pet. filed) (citing Baker, 812 S.W.2d at 55).
  
The burden of proving a penalty defense is on the party challenging the liquidated damages clause. Baker, 812 S.W.2d at 55; see also Urban Television Network Corp. v. Creditor Liquidity Solutions, L.P., 277 S.W.3d 917, 919 (Tex. App.—Dallas 2009, no pet.). Generally, the party asserting this defense must prove the amount of the other party’s actual damages, if any, to show that the liquidated damages set forth in the agreement were not an approximation of actual loss. Baker, 812 S.W.2d at 55; TXU Portfolio, 328 S.W.3d at 589. SOURCE: Beaumont Court of Appeals - 09-10-00361-CV - 5/19/11 (Thus, the liquidated damages provision for the payment of $20,000 was not a reasonable forecast of just compensation for any allowable damages resulting from [ PARTY'S ] breach of the agreement. We hold the liquidated damages clause is unenforceable.)
 
RELATED CASELAW CLIPS:
 
We enforce a liquidated damages clause if (1) the harm caused by the breach is incapable or difficult of estimation, and (2) the amount of liquidated damages is a reasonable forecast of just compensation. See Phillips v. Phillips, 820 S.W.2d 785, 788 (Tex. 1991). An assertion that a liquidated damages provision constitutes an unenforceable penalty is an affirmative defense, and the party asserting penalty bears the burden of proof. See Urban Television Network Corp. v. Liquidity Solutions, 277 S.W.3d 917, 919 (Tex. App.-Dallas 2009, no pet.); Fluid Concepts, Inc. v. DA Apts., LP, 159 S.W.3d 226, 231 (Tex. App.-Dallas 2005, no pet.). Generally, that party must prove the amount of actual damages, if any, to demonstrate that "the actual loss was not an approximation of the stipulated sum." Baker v. Int'l Record Syndicate, Inc., 812 S.W.2d 53, 55 (Tex. App.-Dallas 1991, no writ). If the amount stipulated in the liquidated damages clause is "shown to be disproportionate to actual damages," we should declare that the clause is a penalty and limit recovery to actual damages. Johnson Eng'rs, Inc. v. Tri-Water Supply Corp., 582 S.W.2d 555, 557 (Tex. Civ. App.-Texarkana 1979, no writ); see also TEX. BUS. & COM. CODE ANN. § 2.718(a) (Vernon 2009) ("A term fixing unreasonably large liquidated damages is void as a penalty.").

Whether a liquidated damages clause is an unenforceable penalty is a question of law for the court, but sometimes factual issues must be resolved before the court can decide the legal question. See Phillips, 820 S.W. 2d at 788. For example, in Phillips, the Texas Supreme Court observed that "to show that a liquidated damages provision is unreasonable because the actual damages incurred were much less than the amount contracted for, a defendant may be required to prove what the actual damages were." Id. SOURCE: Houston Court of Appeals - 01-09-00155-CV - 10/21/10 Whether a liquidated damages provision is an enforceable contractual provision or an unenforceable penalty is a question of law. Phillips v. Phillips, 820 S.W.2d 785, 788 (Tex. 1991). To find a liquidated damages provision enforceable, a court must find that (1) the harm caused by the breach is incapable or difficult of estimation, and (2) the amount of liquidated damages called for is a reasonable forecast of just compensation. Phillips, 820 S.W.2d at 788 (quoting Rio Grande Valley Sugar Growers, Inc. v. Campesi, 592 S.W.2d 340, 342 n.2 (Tex. 1979)). The difficulty of estimation of harm must have existed at the time the contract was executed. See Murphy v. Cintas Corp., 923 S.W.2d 663, 666 (Tex. App.-Tyler 1996, writ denied).

SOURCE: Austin Court of Appeals - 03-09-00063-CV - 6/11/10

A valid liquidated damage provision estimates in advance the just compensation to a party accruing from the failure to perform certain contractual obligations. See Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 664 (Tex.2005); Stewart v. Basey, 150 Tex. 666, 245 S.W.2d 484, 486 (1952). In general, the issue of whether a contractual provision is an enforceable liquidated damage clause or an unenforceable penalty is a question of law for the court. See Phillips v. Phillips, 820 S.W.2d 785, 788 (Tex.1991). In making this determination, we examine whether the harm caused by the prospective breach of the contract is incapable or difficult of estimation and whether the amount of liquidated damages is a reasonable forecast of just compensation. Id.; Baker v. Int'l Record Syndicate, Inc., 812 S.W.2d 53, 55 (Tex.App.-Dallas 1991, no writ). The evidence concerning the difficulty of estimation and the reasonableness of the damages forecast must be viewed as of the time the contract was executed. Baker, 812 S.W.2d at 55. The party asserting that the provision is an unenforceable penalty has the burden of proof. See Fluid Concepts, Inc. v. DA Apartments Ltd., P'ship, 159 S.W.3d 226, 230-31 (Tex.App.-Dallas 2005, no pet.). Where, as here, the parties have filed cross-motions for summary judgment, we may reverse and render the judgment that the trial court should have rendered. See CU Lloyd's of Tex. v. Feldman, 977 S.W.2d 568, 568 (Tex. 1998) (per curiam).
 
SOURCE: Dallas Court of Appeals - 05-08-01584-CV 7/27/10

Wednesday, May 18, 2011

Liquidated Damages vs. Unenforceable Penalty

ARE LIQUIDATED DAMAGES CLAUSES ENFORCEABLE? – STIPULATED DAMAGES OR UNENFORCEABLE PENALTY?

“The term 'liquidated damages' ordinarily refers to an acceptable measure of damages that parties stipulate in advance will be assessed in the event of a contract breach.” Flores v. Millenium Interests, Ltd., 185 S.W.3d 427, 431 (Tex. 2005); see also Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 664 (Tex. 2005) (“[l]iquidated damages clauses fix in advance the compensation to a party accruing from the failure to perform specified contractual obligations”). Whether a contract term is a liquidated damages clause is a question of law for the court. Valence Operating Co., 164 S.W.3d at 664.
 
If a court determines that a contract term is a liquidated damages clause, the court may then determine whether the clause is enforceable, or whether it is an unenforceable penalty. The policy underlying the prohibition against penalties is to ensure that a party to a contract receives “just compensation,” that is, “neither more nor less than his actual damages.” Phillips, 820 S.W.2d at 788 (quoting Stewart v. Basey, 150 Tex. 666, 245 S.W.2d 484, 485-86 (1952)). In order to enforce a liquidated damages provision and determine the provision is not a penalty, “the court must find: (1) that the harm caused by the breach is incapable or difficult of estimation, and (2) that the amount of liquidated damages called for is a reasonable forecast of just compensation.” Phillips, 820 S.W.2d at 788 (quoting Rio Grande Valley Sugar Growers, Inc. v. Campesi, 592 S.W.2d 340, 342 n.2 (Tex. 1979)).
 
The party asserting that a liquidated damages clause is an unenforceable penalty bears the burden of proof. Urban Television Network Corp. v. Liquidity Solutions, Ltd., 277 S.W.3d 917, 919 (Tex. App.-Dallas 2009, no pet.) (citing Murphy v. Cintas Corp., 923 S.W.2d 663, 665-66 (Tex. App.-Tyler 1996, writ denied)).

CONTENTION MUST BE RAISED AND PLEADED AS AN AFFIRMATIVE DEFENSE
  
Whether a contractual provision is an unenforceable penalty and not a liquidated damage clause is an affirmative defense. See Tex. R. Civ. P. 94; Phillips v. Phillips, 820 S.W.2d 785, 789 (Tex. 1991) (“Although penalty is not among the affirmative defenses enumerated in Rule 94, Tex. R. Civ. P., the listing in that rule is not exclusive. Penalty is, in the language of the rule, a 'matter constituting an avoidance or affirmative defense' [citations omitted].”)
  
SOURCE: Dallas Court of Appeals - 05-09-00586-CV - 5/18/11

Tuesday, October 27, 2009

Claim for LIQUIDATED and UNLIQUIDATED Damages in Default Judgment Context

   
EFFECT OF DEFAULT BY DEFENDANT WHO WAS PROPERLY SERVED
A defendant who defaults admits all allegations of facts except unliquidated damages. See Holt Atherton Indus., Inc. v. Heine, 835 S.W.2d 80, 83 (Tex. 1992); Stoner v. Thompson, 578 S.W.2d 679, 684-85 (Tex. 1979).
 
WHEN CAN DEFAULT JUDGMENT BE HAD FOR LIQUIDATED DAMAGES?
When a plaintiff's claim is liquidated, and proven by an instrument in writing, the plaintiff may be awarded damages without the necessity of a hearing or the presentation of evidence. Burrows v. Bowden, 564 S.W.2d 474, 475 (Tex. Civ. App.-Corpus Christ 1978, no writ); Tex. R. Civ. P. 241.
 
WHAT MAKES A CLAIM "LIQUIDATED"?
A claim is liquidated if the amount of damages caused by the defendant can be accurately calculated from: (1) the factual, as opposed to conclusory, allegations in the petition, and (2) an instrument in writing. Freeman v. Leasing Assocs., Inc., 503 S.W.2d 406, 408 (Tex. Civ. App.-Houston [14th Dist.] 1973, no writ). A default judgment does not establish allegations pertaining to unliquidated damages. First Nat'l Bank of Irving v. Shockley, 663 S.W.2d 685, 689 (Tex. App.-Corpus Christi 1983, no writ). If damages are unliquidated or not proved by an instrument in writing, the court must hear evidence as to damages before a default judgment may be granted. Tex. R. Civ. P. 243.
 
ATTORNEYS FEES ARE UNLIQUIDATED (BUT CAN BE PROVEN UP BY AFFIDAVIT) Attorney's fees are by their very nature unliquidated. The reasonableness of attorney's fees, in the absence of a contract therefore, is a question of fact and is an unliquidated demand for which the trial court entering a default judgment should hear evidence. First Nat'l Bank of Irving, 663 S.W.2d at 691.
 
DEEMED ADMISSIONS MAY BE USED AS SUBSTITUTE FOR OTHER PROOF
A trial court may be able to ascertain the amount of damages and attorney's fees in a default judgment based on a request for admissions. Sherman Acquisition II LP v. Garcia, 229 S.W.3d 802, 813 (Tex. App.-Waco 2007, no pet.). A plaintiff may serve a request for admissions as part of its petition, and when the defendant fails to file an answer or other response, those requests are deemed admitted. Id. at 811-12 (citing Tex. R. Civ. P. 198.2(c)). Deemed admissions may be employed as proof, and once admissions are deemed admitted by operation of law and where the admissions fully support each element of a cause of action, including damages, they will fully support a judgment based thereon. This is because unanswered requests for admissions are deemed admitted without the necessity of a court order and any matter thus admitted is conclusively established as being true. Id. at 812-13 (citing Tex. Rs. Civ. P. 198.2(c), 198.3). Thus, the facts admitted may not be contradicted by evidence at the trial. Id. at 813 (citing Marshall v. Vise, 767 S.W.2d 699, 700 (Tex. 1989)).
 
SOURCE: 05-07-01730-CV (Dallas Court of Appeals)(10/26/2009) (credit card debt suit)



Thursday, September 3, 2009

Proof of damages for default judgment purposes: proving up liquidated vs. unliquidated damages


WHAT IS CONSIDERED ESTABLISHED WITHOUT A NEED FOR PROOF IN THE DEFAULT JUDGMENT CONTEXT?

In a no-answer default judgment, the failure to file an answer operates as an admission of the material facts alleged in the petition, except as to unliquidated damages. Holt Atherton Indus., Inc. v. Heine, 835 S.W.2d 80, 83 (Tex. 1992).
 
A claim for damages is liquidated if the amount of damages can accurately be calculated by the court from the factual, as opposed to the conclusory allegations in the petition and written instruments. Argyle Mech., Inc. v. Unigus Steel, Inc., 156 S.W.3d 685, 687 (Tex. App.-Dallas 2005, no pet.); see also Novosad v. Cunningham, 38 S.W.3d 767, 773 (Tex. App.-Houston [14th Dist.] 2001, no pet.) (suit to recover amount due for professional services was liquidated claim proved by written instruments where plaintiff attached original instruments to verified petition and motion for default judgment).
 
When damages are unliquidated, the judge must “hear” evidence on the damages. See Argyle Mech., Inc., 156 S.W.3d at 687; see also Tex. R. Civ. P. 243. In contrast, “if the claim is liquidated and proved by an instrument in writing, the damages shall be assessed by the court, or under its direction, and final judgment shall be rendered therefor . . . .” Tex. R. Civ. P. 241.
 
SOURCE: DALLAS COURT OF APPEALS - 05-07-01449-CV (credit card debt suit)